The PatchBox pipe repair system - Repair pipes from 100mm to 1200mm diameter!Click here to visit Sewer Center - Equipment with service.

Sewer Center,
Queen Street,
Stourton,
Leeds.
LS10 1SL
Tel: 0845 125 95 95
Fax: 0845 125 95 98

Home | Application Systems | Buy Patch Box From Sewer Center

WRc External Hydrostatic pressure trial of a Konudur 250 OM-PL cured in place repair

Introduction  
The objective of this test was to investigate the leak tightness of the Konudur 250 OM-PL local lining system under external hydrostatic water pressure in accordance with the test specified in Appendix C of the Specification for Local Sewer Repairs (WRc Ref: UC 3248/Appendix B).

The cured in place patch repair was made from three layers of glass fibre fabric which were laid in turn onto a polyethylene release film and impregnated with a polyurethane resin. The patch was wrapped around an inflatable packer, inserted into the clay pipe to be repaired (which had a specified defect) and compressed against the pipe wall whilst it cured at ambient temperature for approximately two hours. The performance of the lining was then tested using the WRc external pressure rig.
 
Test Rig Specification
The WRc test rig has been designed and constructed to allow external water pressure to be applied to a defective clay pipe which has been repaired using a local lining system.

Photograph 1 shows the hydrostatic test rig and a schematic of the rig is also shown in Figure 1. The rig consists of a 20" steel tube with caps welded to the ends. Two number DN 350 Viking Johnson Maxidaptors (16 bar pressure rating) are bolted to these end caps. This is then assembled around the outside of the clay test pipe and the Maxidaptors tightened to provide a water tight seal between the rig and the pipe. Inlet and outlet valves enable water to be pumped into the annulus between the pipe and steel tube. The pressure in the rig is monitored using a pressure gauge connected to the outlet valve.
 
Production of Test Piece
A DN 300 clay pipe (OD 380 mm) pipe approximately 1.5 m long was lined with a 1.2 m long patch repair. The defect consists of a 100 mm x 100 mm hole in the pipe wall. Lining took place at the WRc Swindon Offices and was witnessed by a WRc member of staff.

During the installation of the patch repair, the defect was placed at the pipe springing to prevent build up of resin in the hole. The outside of the clay pipe was then coated with varnish to prevent water permeating through the pipe wall during the hydrostatic test.
 
Leakage Failure Criteria
The aim of the test was to determine whether the patch repair system under investigation can prevent infiltration of ground water through the defective clay pipe. The failure criteria for leakage is set at 0.5 litres per linear meter per meter of nominal diameter over a 30 minute period, which is the permissible rate of infiltration for new sewers, as specified in Sewers for Adoption. The worst ground water loading conditions to which a sewer will be exposed will be the maximum depth of the pipe (to invert) in fully saturated ground. For the purpose of this test, a pressure of 1 bar (approximately 10 m head) was used, 10 m being the maximum ground water loading a sewer is likely to experience in the UK.
 
Test procedure
The procedure for testing for leak tightness is as follows:
1. The test rig was pressured to 10 m head (1 bar) for a period of 2 hours.
2. Any water loss from the rig was collected and measured over the next 30 minutes.

If the measured flow exceeded 0.5 litres per linear meter per meter of nominal diameter, then the lining was deemed to have failed. Failure flow rates are given below in table 1.

Table 1. Failure flow rates for leak tightness in the hydrostatic rig.
Length of local lining Failure flow rate
0.5 m 75 ml
1.0 m 150 ml
1.2 m (Konudur 250 OM-PL patch) 180 ml

Results
Tested at WRc Swindon on the 12th October 1999.

The test rig was pressurised to 1 bar and the pressure maintained for 2 hours. The sample wept at the 4 o'clock position approximately 225 mm from one end of the patch after 15 minutes. The weeping was initially from a single pin sized defect but at the end of the 2 hour pre-conditioning period there were a total of five defects within the general area of the initial weeping.

The 1 bar pressure was then maintained (by pumping for a further 30 minutes and the flow (loss) of water from the patch repair was recorded. The loss of water during the 30 minute period was 54 ml which is well within the 180 ml allowance for a 1.2 m long repair.

The lining therefore passed the leakage test.

The following table summarises the results of the hydrostatic test.

Table 2. Summary of Results from Hydrostatic test
Lining System Recorded Flow Leak Test
Konudur 250 OM-PL 58 ml Pass
 
Conclusion
The Konudur 250 OM-PL patch repair system passed the external hydrostatic water pressure (leak tightness) test carried out in accordance with Appendix C of the specification for Local Sewer Repair.

This is a one off test and doesn't constitute a full WRc Approval
 

Technical Information
Konudur 250 OM-PL resin specification